Reconstruction Time Line of CBE Summer Lab Space

Written By: Claire Massey

Categories:

John C. Kuetemeyer Instructional Laboratory & Donald E. Baldovin Process Operations Laboratory


Summer lab space before reconstruction with old tables and chairs.
May 2019

Department submits plan to upgrade and expand the CBE instructional lab space.


June 2019

Department receives lead gift and receives additional major gifts throughout 2019-2020.


Fall 2020-Spring 2021

Develop initial scope and select architects.


October 2021

Brick breaking ceremony


Dec 2021

Board of Regents approve plans.

Regina Murphy wields a sledge hammer  against a wall to celebrate the brick breaking ceremony

Old tables and chairs are being cleared out to make way for renovation of the new lab.
Spring-Summer 2022

Set up temporary lab on the 4th floor and clear out B103 and B209.


Summer of 2022

Post project for bids and select JP Cullen as the General Contractor.


Fall 2022

Construction begins. Contractors complete most of the demolition by December 2022 with excavation continuing into January 2023.

Rubble and demolition equipment for operations lab

Spring 2023

Install windows, walls, floors and drains, and finish most mechanical, electrical, plumbing and fire protection. Add roof and masonry walls to B209 and install hoods, lab benches and shelving in B103.

New windows installed
Masonry walls installed in B209 laboratory

Summer 2023

Complete drywall, B209 elevator, and finishing touches, such as metal stairs and railings. Materials start migrating back into B103.


Fall 2023

Install air handling unit and a final clean opens up the B103 lab for the first class.


Spring 2024

Reconstruction of distillation column and other large equipment starts in B209.

Students Draft the First Fermentation Lab.


April 19th, 2024

Grand Lab Re-Opening Celebration


Summer 2024

First summer lab takes place in the new space.